Lagos- Ibadan Rail Project: Laying of Track Reaches 123km Out of 156km

0
182


ed77b2e3 lagos ibadan rail projec Lagos- Ibadan Rail Project: Laying of Track Reaches 123km Out of 156km

The Minister of Transportation, Mr Rotimi Amaechi, said 123km of the 156 km stretch of the Lagos-Ibadan standard guage rail project hds been completed.

Amaechi made the disclosure on Friday during his routine inspection of the project along Kila, Olodo, Ilugun corridor of the track in the outskirts of Ogun State.
He said the project had been completed up to Kila village, a settlement on the outskirts of Ogun towards Oyo State.

“We are already moving towards Ibadan, the track laying is now in Kila, a town on the outskirts of Ogun.
“In less than a month from now, we should be in Ibadan with the rate the work is going,” he said.

The Minister also said that he would inspect the Apapa port and its connection to the standard guage rail to address the challenges of traffic gridlock in the area.
“We will be visiting the ports tomorrow to address some of the issues we have there.
“It’s imperative that the Apapa ports must be connected to the…



Source: Thisday Newspaper