Second Niger Bridge’s construction hits 44.6%

0
270


The construction work at the second Niger Bridge would soon be completed as the work already done hits 44.6 per cent.

Minister of Power, Works and Housing, Babatunde Fashola

The Federal controller of works in Anambra, Mr Innocent Alumonah, confirmed the progress of work on the bridge that is linking Asaba in Delta and Onitsha in Anambra.

He said that construction firm, Julius Berger, has also accomplished about 85 piles of 914 millimeter in diameter in different axis, Leadership“>Leadership reported.

“The contract was split into phases. Phases 1 to phase 3 have been successfully accomplished and we are now on early works in phase 4. Part of this early works phase 4 forms part of the main contract.

“So far, the 1.2 kilometer sand filling of the road at the Asaba end has reached the height of 2.2 meters out of the expected five meters.

“At the Onitsha end, we have done a lot…