Amaechi explains delay over Eastern rail line

0
272


Abuja – The Minister of Transportation, Mr Rotimi Amaechi, has denied the alleged exclusion of Eastern rail line from Port Harcourt to Maiduguri in the ongoing nationwide rail construction and modernisation.

Shops erected on rail-line

He made the denial when he appeared before the Senate Joint Committee on Land Transport, and Local and Foreign Debts, chaired by Sen. Gbenga Ashafa.

Amaechi said contrary to the claim of exclusion, there was only delay in the execution of the project.

He said the delay was due to bureaucratic bottlenecks caused by the Public Procurement Act.

According to him, the Public Procurement Act is very tedious, stressing “it takes a long time to conclude the process”.

Amaechi added that railway project was capital intensive, noting that the Federal Government did not have sufficient fund to implement the project across the country at the same time.

He…



Read More…..Vanguard Newspaper